Which building inspections does a Hamilton build need?

Every Hamilton permit comes with City inspections at set stages, mandatory under the Ontario Building Code. A new house or addition usually has a pre-construction meeting, footings, backfill, plumbing, radon, framing, insulation and an occupancy or final inspection. The City completes a request within 2 business days, and the permit and approved drawings must be on site. JDT Construction writes the stages into each job's schedule.

When does each inspection happen?

At the stage just before the work would be covered up. These are the City's stages that apply to most houses, additions and ADUs, with the City's own timing (City of Hamilton, Building Inspections, read November 5, 2026):

City of Hamilton inspection stages for a house, addition or ADU
InspectionBook it
Pre-construction on-site meetingBefore construction starts
FootingsBefore the footings are poured
BackfillBefore the foundation excavation is backfilled
Sanitary sewer, storm sewer, water serviceBefore each line is backfilled
Building drainsBefore the radon barrier goes in
RadonBefore the basement slab is poured
Underslab insulationBefore the slab is poured
Plumbing rough-inWhen the supply, drain and vent piping above ground is in
HVAC rough-inWhen the ductwork is in
StructuralWhen framing is done, before insulation; the plumbing, HVAC and electrical rough-ins come first
Air barrierBefore the above-grade insulation
Insulation and vapour barrierBefore drywall
Fire separationsWhen each side is taped and mudded
Fire protection systemsWhen smoke and CO alarms and other life safety parts are in
OccupancyAt substantial completion, before anyone moves in
GradingWhen final grading is done to the approved plan
FinalWhen all the permitted work is complete

Before the footings there is one step that is not the City's: buried lines have to be marked, as locates before you dig explains. Not every job gets every stage: a deck has no plumbing rough-in. The pre-construction meeting is where the inspector goes through required inspections for the scope of work.

What happens if a stage is missed?

The City may ask for the work to be opened up. In its words, Failure to get an inspection at the proper stages may require you to uncover work that was completed. (City of Hamilton, Building Inspections, read November 5, 2026) Grading, where it applies, has to be done before the final inspection, and on infill houses the City asks for a final grading certificate from the consultant at the grading inspection.

Which inspections are new for a new home?

Radon and occupancy. Hamilton requires soil gas protection under the slab of every new low-rise home and residential addition, inspected before the slab is poured; radon protection in new homes covers the two options. And a new house needs an occupancy inspection before anyone lives in it; the City says the request must be accompanied by the appropriate Occupancy Application Form.

Who books them?

Whoever the permit and the contract say. Requests go through the City's online portal or by phone, with the permit number, the address and the type of inspection. Electrical inspections are separate: they are booked with the Electrical Safety Authority, explained in who files the electrical permit. On a JDT Construction Inc. job, inspection stages are written into the schedule on the project page so you can see what is next. How the permit itself is applied for is in who applies for a building permit.